Gusinoozerskaya SDPP

Reconstruction of coal-based generating unit No. 4 of 210 MW capacity

Customer – JSC INTER RAO – Electrogeneration
Prime Contractor – JSC Energia-Service
General Designer – JSC Lonas Technology

The power unit capital improvement increased the power supply reliability of Zabaikalsky Krai, Republic of Buryatia and Irkutsk Region consumers, which encouraged further development of the region economy.

Project description

The Project provides for technical re-equipment of the coal-based generating unit No.4 of Gusinoozerskaya SDPP including correction of existing design documentation, replacement of out-dated and physically worn-out equipment. The installed capacity of the power generating unit under construction is 210 MW. Construction of power generating unit No.4 was completed in the 1th quarter 2013.

Main equipment

  • Steam turbine plant of К-210-130 type, manufactured by JSC Power Machines;
  • Boiler unit Ep-640-140, manufactured by JSC Sibenergomash.
Reconstruction of the power generating unit No. 4 of Gusinoozerskaya SDPP is sufficiently enhancing reliability of electric power supply to consumers of Zabaikalie Region, Republic of Buryatia and Irskutsk region.

Technical and economic performance

Designed electric capacity of the power generating unit to be put into operation 210 MW
Installed capacity of the power generating object including put into operation of the new power generating unit 1 130 MW
Planned annual electric power generation by the power generating unit 1 071 mln kW*per year
Main project fuel Brown coal of 3BP mark of Pereyaslavskiy open cut
Fuel consumption rate 342.164 th. tonne of fuel equivalent/per year
Degree of efficiency of electric power by output 36.70%
ICUF 58.22%
Specific reference fuel consumption for electric power output 335 GOE/kW*per hour