Nizhnevartovskaya SDPP

Construction of the 400 MW Unit 3.1

Customer - JSC Nizhnevartovskaya SDPP 

Turnkey construction and launch of the 400 MW Generation Unit 3.1 at Nizhnevartovskaya SDPP. The new power generation unit will help to address the shortage of electricity in Nizhnevartovsk District of Khanty-Mansi Autonomous Okrug, an important prerequisite for further development of the regional oil and gas industry.  The Power Plant was launched in 2014.

Main equipment

  • General Electric PG9351(FA) gas turbine with 324H 50 Hz generator
  • General Electric D12 steam turbine with 9А5 generator
  • Atomenergomash P-143 heat recovery steam boiler 

Technology and Economics

New power generation capacity 400 MW
Overall installed capacity including the new unit                                     2000 MW
Fuel SDG (stripped dry gas)
Fuel consumption 608.2 million cubic meters per year
Electric power efficiency 54.5 %
Equivalent fuel consumption (electricity) 225 g/kWh

LLC Inter RAO — Engineering